A data centre is not a building. Stop managing it like one.

October 2026 6 min read

A data centre is a power and cooling system with a building around it. The building is the simple part. The cost, the risk and the programme sit in the electrical and mechanical systems inside it, and in the grid connection that feeds them.

Yet most data centres are still procured and managed through a professional structure designed for buildings. A project manager owns the programme. A cost consultant owns the budget. They report separately, on separate cycles, to a client who has to join the two together. On an office or a school, that gap is expensive. On a data centre, it is where the project is won or lost.

The building is the small part

On a conventional building, the frame, envelope and fit out make up most of the cost. The services matter, but they follow the architecture.

A data centre reverses that order. Transformers, switchgear, generators, UPS systems, cooling plant and the controls that tie them together carry most of the capital cost. They also carry most of the programme risk, because much of that equipment is made to order and arrives on lead times measured in months, sometimes more than a year.

When the services are the project, programme and cost cannot be managed as separate subjects. Every decision about plant is a decision about time and money at once.

A chain of dependencies

Data centre delivery runs on a chain. The grid connection sets the energisation date. The energisation date sets when the main electrical plant can be tested. Testing sets when commissioning can start. Commissioning sets the ready for service date. The ready for service date sets when the client starts earning a return.

Each link is both a programme event and a cost event. A transformer that arrives six weeks late does not only move a date on a schedule. It moves the testing window, the commissioning team's mobilisation, the contractor's preliminaries, the cashflow forecast and the funding drawdown. All at once.

In a split consultancy model, those consequences are reported by different people. The programme update shows the delay. The cost report shows pressure on preliminaries a month later. The connection between them is left for the client to make.

"A late transformer moves the programme. The programme moves the cashflow. The cashflow moves the funding. In a split model, three reports describe one problem."

Commissioning is where the gap shows

Commissioning is the point at which every earlier decision is tested. Design choices, procurement decisions, specification changes made to save money and sequence changes made to save time all surface here, as performance or as failure.

Commissioning on a data centre runs through defined levels, from factory testing of individual equipment to integrated systems testing of the whole facility under load. It is specialist work, normally carried out by an appointed commissioning agent. But the outcome is decided long before the agent arrives on site.

If the commissioning agent is appointed late, briefed loosely and measured against nothing in particular, the problems found at integrated systems testing become delays and claims. If the agent is appointed early, set clear performance indicators and tracked against them throughout, commissioning becomes a planned stage of delivery rather than a period of discovery.

That requires someone who holds the programme, the cost and the supply chain together, from procurement onwards.

The funder sees the gap first

Data centres are funded against a ready for service date. Investors, lenders and operators are not interested in a programme in isolation or a cost report in isolation. They want to know whether the facility will be ready when committed, at the cost committed, to the resilience specified.

When programme and cost are reported separately, the funder receives two documents that do not always agree, prepared weeks after the period they describe. The questions that follow take time to answer, because the answers have to be reconciled between two consultancies before they can be given.

When programme and cost are managed as one discipline, the funder receives one position. It is current. It explains the relationship between time and money directly. It can be relied on.

"Funders do not lend against a programme or a cost plan. They lend against a date and a number. Those have to come from the same place."

Scale multiplies the problem

Data centre programmes rarely stop at one site. Operators build portfolios, often several facilities at different stages of development at the same time.

Every weakness in the delivery model repeats across the portfolio. If governance depends on individuals, it varies from site to site. If reporting is assembled by hand, it arrives late from every site at once. If lessons from one commissioning programme are not captured, the next site learns them again at full cost.

A portfolio needs a delivery model that is consistent by design. The same stage gates, the same reporting, the same supply chain standards, applied to the tenth site as rigorously as the first.

What integrated delivery looks like

On a data centre, integrated delivery means one lead consultant holding programme, cost, procurement and governance as a single discipline.

It means a professional team assembled from people who have delivered data centres before: designers, MEP and power consultants, contractors and commissioning agents, each prequalified before they join the programme and each measured against agreed performance indicators.

It means procurement strategy built around the plant that drives the programme, with long lead equipment ordered to the dates that matter and tracked from order to delivery.

It means one live view of programme, cost and risk across every site, available to the client and the funder without waiting for a monthly report.

None of this is complicated. It simply requires a structure in which nobody is responsible for only half of the answer.

"One discipline. One position. Programme and cost managed together, from grid connection to ready for service."

Why this matters now

In September 2024, the UK designated data centres as Critical National Infrastructure. The designation reflects what operators already knew: these facilities are now essential to the economy, and the scrutiny on how they are delivered has increased accordingly.

Demand is not slowing. Artificial intelligence and high performance computing are driving facilities that are larger, denser and more power hungry than those that came before them. Grid capacity is constrained. Equipment lead times are long. Timescales are short.

In that environment, the old structure of separate programme and cost advice is not a neutral choice. It is a source of delay, cost and risk in its own right. The clients delivering the next generation of data centres need a delivery model built for the asset, not for the buildings the industry was organised around.

Lestari Project Services is lead project and commercial management consultancy on a national data centre programme. We manage programme, cost, procurement and governance as one discipline, supported by a proprietary platform that gives clients and funders live visibility across every site.

Our data centre services

Ready to raise the standard?

Tell us about your project and we will come back to you.

Get in Touch